cb resident

Washington, DC

#1 Feb 25, 2013
When will the bridge be open??????
discodonnie

King George, VA

#2 Feb 25, 2013
It is scheduled for March 1, 2013
The Vote

Aylett, VA

#3 Feb 25, 2013
It will not be open on March 1. Could be 10 to 20 days later or more. Will be open by April 1.
vdot

King George, VA

#4 Feb 25, 2013
cb resident wrote:
When will the bridge be open??????
my understanding is they ran into some troubles and re-opening should be June 1st 2013. They will be repaving road behind halls next week they will be down to one lane during the hours of 6 am till 6 pm
more wine please

Washington, DC

#5 Feb 25, 2013
Do you mean Pomona being replaced? It certainly needs it.

“Tidewater 2916661”

Since: Dec 09

Colonial Beach and Wash DC

#7 Feb 25, 2013
The Vote wrote:
It will not be open on March 1. Could be 10 to 20 days later or more. Will be open by April 1.
04/01 would be highly suspect :)
CB Newbie

Silver Spring, MD

#8 Feb 26, 2013
I drove down to the bridge this weekend to take a look and it doesn't look like they will be finished by Friday. The large crain is still up, jersey walls on the sides of the bridge aren't complete and the road leading to the bridge must still be leveled and paved. I also emailed the Vdot project manager asking for an update and they never responded.
wtcsret

Goose Creek, SC

#9 Feb 26, 2013
CB Newbie wrote:
I also emailed the Vdot project manager asking for an update and they never responded.
How dare you attempt to comunicate on such an EXCLUSIVE down line :)

That UP LINE starts at CBTM and ABOVE!:) Granted "Nothing Ventured, Nothing Gained :)(That would be NVNG)
Matt R

Woodbridge, VA

#11 Feb 26, 2013
it was my understanding that the contractor gets fined 5k per day for going beyond the projected end date , now this is a stretch but what do they do with that money , maybe disperse it to the commuters that are spending more fuel and time and wear and tear on there vehicles to drive around the delayed construction , hahaha that'll be the day
yea right

King William, VA

#12 Feb 26, 2013
Can't beleive the contract didn't include agreed upon weather effected project days to allow for unworkable days.
Terry

King George, VA

#13 Feb 26, 2013
Ask the right people and ye shall receive....
I e-mailed the vdot communications person directly and this is the information I received verbatum
I apologize for the lack of information on the project website. We had been planning on a Friday, March 1 opening as scheduled, which is why we hadn't posted any new information.
We did receive new information today. We believe there will be a one-week delay opening Route 205 to traffic at the Tides Mill Stream bridge in Westmoreland County. The detour is now likely to be in place through Friday, March 7. We experienced a delay in the delivery of the beams necessary to build the bridge, which caused a slight delay in the project’s schedule. We regret that this detour will be in place for several additional days.
We are finalizing information with construction officials on site today, and we plan to issue a news release tomorrow once we have official, confirmed information. This is the best information I can provide to you today. We will be happy to send this news release to you directly, and we will also update the project website to reflect the new date for the detour to be lifted.
Best regards,
Kelly Hannon
VDOT Communications
NoTime

Eastville, VA

#14 Feb 26, 2013
CB Newbie wrote:
I drove down to the bridge this weekend to take a look and it doesn't look like they will be finished by Friday. The large crain is still up, jersey walls on the sides of the bridge aren't complete and the road leading to the bridge must still be leveled and paved. I also emailed the Vdot project manager asking for an update and they never responded.
Do you think the Project manager has time to sit around and answer e-mails all day?
Some Old Navy Dude

King George, VA

#15 Feb 26, 2013
In other words, business as usual. Bend over, thank you very much.

Did anyone think this was really gonna be done by the end of February?

HAHAHAHAHAHAHA!

Since: Oct 08

King George, VA

#16 Feb 26, 2013
Terry wrote:
Ask the right people and ye shall receive....
I e-mailed the vdot communications person directly and this is the information I received verbatum
I apologize for the lack of information on the project website. We had been planning on a Friday, March 1 opening as scheduled, which is why we hadn't posted any new information.
We did receive new information today. We believe there will be a one-week delay opening Route 205 to traffic at the Tides Mill Stream bridge in Westmoreland County. The detour is now likely to be in place through Friday, March 7. We experienced a delay in the delivery of the beams necessary to build the bridge, which caused a slight delay in the project’s schedule. We regret that this detour will be in place for several additional days.
We are finalizing information with construction officials on site today, and we plan to issue a news release tomorrow once we have official, confirmed information. This is the best information I can provide to you today. We will be happy to send this news release to you directly, and we will also update the project website to reflect the new date for the detour to be lifted.
Best regards,
Kelly Hannon
VDOT Communications
This information is correct... Just got a call from a Scott S. at VDOT and due to at least 3 rain events and the long stretches of cold at night they have been running heaters to help cure the concrete. I was also informed that as of this time there is no sheduled work to Pamona Road behind Hall's. Scott said he would jump on Topix tonight after meeting and post an update. He was thinking at the time that it would be open the end of the first week in March (approx the 7th)... the next project is to be the bridge on Rt 205 going towards Oak Grove, the Mattox Bridge.

Since: Oct 08

King George, VA

#17 Feb 26, 2013
NoTime wrote:
<quoted text>
Do you think the Project manager has time to sit around and answer e-mails all day?
They do if you ask nicely... ;-)
Anyone Read the Paper

Charlotte, NC

#18 Feb 26, 2013
VDOT originally promised that any construction not finished within the projected four-month closing would be shoulder work and would not hinder the re-opening of the bridge to thru traffic.
The bridge was originally scheduled to reopen March 1, and Dave Brown says that the work is right on schedule. He reported to Town Manager Val Foulds on Tuesday, however, that the bridge will be open in early March. Brown said he was being conservative, in case of inclement weather that may delay the project’s completion.
The project was originally delayed by one day due to Hurricane Sandy, but officials stated that the delayed start would not impact the March 1 completion date.
The detour will continue to be designated as Route 631 (Longfield Road) until the bridge project is complete.
http://www.journalpress.com/index.php/colonia...

Since: Feb 13

Silver Spring, MD

#19 Feb 26, 2013
Sounds like they didn't plan on keeping the public informed on the progress!!!! Then again who gives a crap about the people who the detour effects... Just keep wasting our time and our gas money. That's fine!!!!

Since: Feb 13

Location hidden

#21 Feb 27, 2013
CB-Newbie wrote:
Sounds like they didn't plan on keeping the public informed on the progress!!!! Then again who gives a crap about the people who the detour effects... Just keep wasting our time and our gas money. That's fine!!!!
Welcome to Government.

Since: Feb 13

Silver Spring, MD

#22 Feb 28, 2013
They finally updated the vdot website and its official... One more week of the hell detour!!!

Since: May 10

Location hidden

#23 Feb 28, 2013
Here's the press release:

ROUTE 205 DETOUR TO CONTINUE FOR ONE WEEK

Ridge Road in Westmoreland County will now open to traffic on Friday, March 8

FREDERICKSBURG – Route 205 (Ridge Road) in Westmoreland County will open to traffic at the newly rehabilitated Tides Mill Stream bridge on Friday, March 8.

The bridge has been closed to traffic since November 2, 2012. Traffic has been following a detour route on Route 631 (Longfield Road).

The detour was scheduled to be lifted by Friday, March 1. The opening has been delayed one week due to a delay in the delivery of beams needed to complete the bridge deck.

The beams have been delivered and installed, and paving work to complete the project will take place next week.

The project is still on schedule to be finished by March 15. Motorists should expect occasional single lane closures during daytime hours until this date.

The Virginia Department of Transportation (VDOT) is performing a major rehabilitation of the bridge, which is structurally deficient. The bridge was built in 1933.

This project rehabilitated the bridge's superstructure, as well as made minor repairs to the concrete substructure of the bridge.

A contract for this $3.7 million project was awarded to Bryant Contracting, Inc.

Tell me when this thread is updated:

Subscribe Now Add to my Tracker
First Prev
of 2
Next Last

Add your comments below

Characters left: 4000

Please note by submitting this form you acknowledge that you have read the Terms of Service and the comment you are posting is in compliance with such terms. Be polite. Inappropriate posts may be removed by the moderator. Send us your feedback.

Colonial Beach Discussions

Title Updated Last By Comments
Add a word, drop a word (Oct '13) 3 hr _FLATLINE-------- 5,355
add a word, drop a word 2 (Mar '12) 3 hr _FLATLINE-------- 4,840
add a word, drop a word (Apr '11) 3 hr _FLATLINE-------- 17,168
A to Z: names of music artists (Apr '14) 3 hr Honest Babe 793
The Famous Name Game (Apr '14) 3 hr Honest Babe 344
A to Z: names of cities, towns, states, places ... (Apr '14) 3 hr Honest Babe 400
Song Title Game (Apr '14) 5 hr Honest Babe 678

Colonial Beach Jobs

More from around the web

Personal Finance

Colonial Beach Mortgages