Stress at Pilgrim Plant?
Mike Mulligan

Brattleboro, VT

#1 Nov 20, 2013
Due to Leakage and Setpoint Drift" was submitted on March 31, 2013 (Reference 1), with a target schedule of September 30, 2013 to submit a Supplement to the LER, after completing the root cause analysis.
Since then the vendor (Target Rock) has issued a 10 CFR Part 21 Notification,(Reference 2) confirming defects in safety relief valve bellows. Entergy is incorporating the information related to the reported defect into the root cause analysis. Due to the recent refueling outage, emergent plant events, and vendor 10 CFR, Part 21 Notification, Pilgrim resources were diverted to address the emergent work activities. As such, the review and approval of the SRV-3B root cause incorporating the vendor Part 21 Notification and the lessons learned from the events is taking longer time than expected. Accordingly, the LER Supplement is expected to be submitted by February 14, 2014.

Tell me when this thread is updated:

Subscribe Now Add to my Tracker

Add your comments below

Characters left: 4000

Please note by submitting this form you acknowledge that you have read the Terms of Service and the comment you are posting is in compliance with such terms. Be polite. Inappropriate posts may be removed by the moderator. Send us your feedback.

Brattleboro Discussions

Title Updated Last By Comments
News Road Pitch investors ride motorcycles into Brat... Jun 23 internet troll 1
Happy Zombie Jesus Day (Apr '15) Jun 21 SDIPN dot Net 25
Actor Says Obama Stole His Persona (Nov '13) Jun 19 Lhdollbaby 11
Seek God And Receive Answers For Your Troubles (Apr '15) Jun 14 Light For All 4
Looking for Guy Who Tried to Sell Heroin To My Kid (Sep '15) Jun 14 Light For All 7
Angels Are Watching You! (Apr '15) Jun 14 Light For All 8
News Habitual offender gets 15-24 months in jail (Aug '09) Jun 14 Light For All 8
More from around the web

Personal Finance

Brattleboro Mortgages